Owner-ready daily report preview
Sample report output
Ridgeview Tenant Improvement
Weather64 F, overcast AM, clear PM
Crew9
Subs3
Open items2
Work completed
Completed level 2 metal stud layout, installed corridor top track, roughed in electrical home runs at suite 204, and stocked drywall at the north stair staging area.
Subcontractor manpower
| Trade | Company | Crew | Hours | Work area |
|---|---|---|---|---|
| Carpentry | Northline Interiors | 4 | 8.0 | Metal stud layout and top track |
| Electrical | Brightway Electric | 2 | 7.5 | Suite 204 home runs |
| Drywall | Mesa Board | 3 | 4.0 | Material stock and staging |
Delays and issues
- Delay / Open: Level 2 east wall hold pending owner millwork dimension confirmation.
- Issue / Closed: Drywall delivery arrived 45 minutes late; crew resequenced to corridor layout.
Materials and equipment
- 5/8 inch Type X drywall (72 sheets): Stocked north stair staging.
- 19 ga metal studs (34 bundles): Level 2 layout.
- Scissor lift (1): On site, charging overnight.
Safety and visitors
Morning JHA completed. No injuries. Temporary guardrail at stair opening checked after lunch.
Owner rep walk with K. Chen at 10:30 AM. City electrical inspector arrived 1:15 PM; rough-in corrections noted.
Photo placeholders
Photo 1: ProgressLevel 2 corridor top track complete
Photo 2: MaterialsDrywall stocked at north stair
Photo 3: SafetyTemporary guardrail checked
Photo 4: VisitorInspection correction note location
SuperintendentM. Alvarez
Prepared byM. Alvarez
Owner / PM reviewOwner PM initials pending